|
1. Prepare replaceable epiploons, sealing and lock rings. 2. Before installation of components carefully wipe them with use of solvent. 3. Before landing of an epiploon grease its sealing sponges, and also pump housing walls with jellied lubricant. 4. Manufacturers recommend to make replacement of a shaft of the pump. 5. Further assembly is made as it should be, the return to an order of dismantle of components, track that shiberny shovels were put in rotor grooves by the rounded ends outside (to an eccentric ring). 6. Working in a diagonal order, tighten bolts of fastening of a back cover of pump assembly with the required effort. 7. In conclusion check smoothness of rotation of a shaft, estimate the size of its side side play. |